Cheyenne Wyoming Park & Recreation Administration
Site Search
Go To Site Search
Greenway Phase III(b) Project Status

 Greenway Phase IIIB Extension
Bid No. M-11-10
Project Status as of August 1, 2010

Project Manager: Todd Feezer, Assistant Director of Parks & Recreation
Percentage Complete:  63%
Estimated Completion Date: August 2010 (Updated from June 2010)
Design Engineer: Ayres Associates
Construction Contractor: Reinman Corp.

Project Description:  Greenway Phase IIIB is a 1.2-mile extension of the east Cheyenne Greenway from College Drive to Hot Springs Avenue along the north side of the UP main line. The project also includes a 75-foot span across the Henderson drainage at the current end of path in the Sun Valley Open Space. Other amenities along this corridor include benches for train viewing, bird watching and nature enjoyment. The path will also provide access to the two softball fields at the VFW Pride Park. The eventual destination of this trail is to tie into the existing Greenway at Norris Viaduct and to provide access in to Holliday Park.

 Project Budget

 

Contract Amount

Paid to Date 

Balance 

 Design

$0.00

$0.00

  $0.00

 Construction Management

$6,000.00

$2,702.25

$3, 297.75

 Construction

$332,328.55

$225,628.90

$106,699.65

 Other Expense (Force Account)

$26,000.00

$8,411.40

$17,588.60

 Other Expense (Specify)

$0.00

$0.00

$0.00

 Other Expense (Specify)

$0.00

$0.00

$0.00

 TOTAL

 $364,328.55

$236,742.55

$127,586.00

Project Budget Source 

 

 Budget Amount

 Paid to Date

 Balance

 Special Purpose Tax Ballot (6th Penny)

$364,328.55

$236,742.55

$127,586.00

 Specify Funding Source

$0.00

$0.00

$0.00

 Specify Funding Source

$0.00

$0.00

$0.00

 TOTAL

 $364,328.55

$236,742.55

 $127,586.00