Project Status
|
Norris Viaduct (Bid No. M-22-08)
Project Status as of 6/1/10
|
Project Manager: Nathan Beauheim
Percentage Complete: 95%
Estimated Completion Date: 7/1/2010
Design Engineer: Olsson Associates
Construction Contractor: Reiman Corp.
Project Description: |
| |
Contract Amount
|
Paid to Date
|
Balance
|
| Design & Construction Management |
$3,935,814.35
|
$3,772,823.16
|
$162,991.19
|
| Construction |
$18,043,936.60
|
$17,252,940.05
|
$790,996.55
|
| Right-of-Way |
$4,560,000.00
|
$4,554,209.18
|
$5,790.82
|
| Steel Girder Fabrication |
$1,059,539.15
|
$1,059,539.15
|
$0.00
|
| Union Pacific Railroad |
$475,000.00
|
$389,785.45
|
$85,214.55
|
| Misc. Expenses |
$150,000.00
|
$147,259.35
|
$2,740.65
|
|
TOTAL
|
$28,224,290.10
|
$27,176,556.34
|
$1,047,733.76
|
| |
Budget Amount
|
Paid to Date
|
Balance
|
| 6th Penny |
$11,000,000.00
|
$11,000,000.00
|
$0.00
|
| 6th Penny Overage |
$1,099,247.00
|
$272,456.93
|
$826,790.07
|
| TEA-21 High Priority Earmark |
$3,283,599.00
|
$3,283,599.00
|
$0.00
|
| SAFETEA-LU FY06 Appropriation |
$792,000.00
|
$792,000.00
|
$0.00
|
| Frontier Refining - Storm Sewer |
$1,500,000.00
|
$1,500,000.00
|
$0.00
|
| Frontier Refining - 4th St. |
$8,000.00
|
$8,000.00
|
$0.00
|
| Frontier Refining - Landscaping/DEQ |
$87,800.00
|
$0.00
|
$87,800.00
|
| BOPU - Construction |
$2,015,233.55
|
$2,063,574.41
|
-$48,340.86
|
| BOPU - Design |
$551,014.01
|
$521,745.43
|
$29,268.58
|
| 06 SLIB for Storm Sewer |
$740,336.00
|
$740,336.00
|
$0.00
|
| 07 SLIB for Norris (incl. Water & Sewer) |
$1,971,258.00
|
$1,971,258.00
|
$0.00
|
| 08 SLIB for Norris |
$4,387,819.00
|
$4,387,819.00
|
$0.00
|
| General Fund |
$38,000.00
|
$38,000.00
|
$0.00
|
| Greenway TEAL |
$282,031.00
|
$223,336.30
|
$58,694.70
|
| Greenway Match (6th Penny) |
$118,284.00
|
$55,834.06
|
$62,449.94
|
| Traffic 5th Penny for Signal Work |
$50,450.00
|
$50,450.00
|
$0.00
|
|
TOTAL
|
$27,925,071.56
|
$26,908,409.13
|
$1,016,662.43
|
|
|